ORMI Plus
Reduction Requests
Position switch IP67.
red-001 · submitted by Thandi Mokoena on 28 Sept 2026, 09:15
pending
no risk
manual · Assembly ShopCurrent min / max
6 / 20
Proposed min / max
4 / 12
Estimated savings
R 9,500
Approval steps
0 / 1
Origin
Manual reduction raised by Thandi Mokoena; risk chosen by requestor: no risk. Open Manual Reduction
Justification
Consumption averaged 2/month over the past 18 months. Lead time only 10 days.
You are reviewing as Technical Approver (on behalf, as Administrator).
Projected impact
Estimated savings
R 9,500
Max reduction · 8 units × R 950R 7,600
Min reduction · 2 units × R 950R 1,900
Total units removed · 10R 9,500
Minimum level2 units (33%)
Current6
Proposed4
Maximum level8 units (40%)
Current20
Proposed12
Cover today
21 days
Cover after reduction
14 days
Supplier lead time is 21 days.
Comments
No comments yet.
Approval chain
- 1
Technical Approver
Anneke Pretorius
Awaiting review
Audit trail
Submitted
Thandi Mokoena · 28 Sept 2026, 09:15
Routed to Technical Approver